Location
Milepost
Project Description
Project Status
Completion Date
Project Cost
(in millions)
Mcleansville
H-7.8 to H-9.9
Lengthened siding; increase siding speed from 10 – 45  mph
Completed
2002
$0.98 Million
Mebane
H-31.8 to H-34.1
Lengthened siding; increase siding speed from 10 – 45  mph
Completed
2003
$0.95 Million
West Durham
(Funston)
H47.9-49.9
Upgraded and extended the siding track from 6,500 feet to 9,000 feet. Installed new No. 20 turnouts to allow trains to travel faster (from 10 to 45 mph) through the siding.
Completed
2003
$2.31M
East Durham
(D&S Junction)
H-56.6 to H-56.9
Replaced a 20 mph at-grade railroad crossing of CSX and NS with a series of switches that permitted raising speed to 79 mph. Constructed 1,300 feet of new track. The new track and switches enable trains to switch tracks faster.
Completed
2004
$2.03
Cary to Greensboro
H-0.0 to H-73.0
Realigned and increased superelevation (banking) of curves
Completed
2005
$2.85 M
Cary to Greensboro
H 0.0 – H73.0
Installed traffic control and communications system to automate train dispatching. The systems enables trains to operate at maximum speeds of 79 mph.
Completed
2004
$10.77 M
Downtown Greensboro
(Elm Junction)
H-0 to H-0.7
Rebuilt the Greensboro junction for higher speeds and improved capacity. Built second track at Greensboro Station.
Completed
2005
$1.27 M
Kannapolis and Salisbury
337.3 and 347.3
Replaced turnouts (switches) to accommodate faster speeds.
Completed
2007
$2.5 M*
East Durham Siding
H-56.6 to H-59.1
Built 10,400 feet of new track to create a new passing siding.
Completed
2007
$6.5 M*
Raleigh to Cary
(Boylan to Fetner)
H-73 to H-81
Improve track and signals to provide 79 mph max. speed and increase track capacity
Track work completed 2005. Work on signals and Fetner junction will be complete in 2009.
2009
$11 M*
Greensboro - High Point
(Cox to Hoskins)
NS Main Line 289.3 to 298.5
Construct 9 miles of a second main track to improve railroad capacity and passenger train reliability.
Under construction
2009
$20 M*
Various
Various projects between Greensboro and Durham
Install crash beams and sensors on various bridges to  protect the railroad from overheight trucks.
Pilot project complete at Gregson St., Durham. Other projects still underway.
2009
$1 M*
Greensboro to Charlotte
284 to milepost 376
Realign and increase superelevation (banking) of curves to increase speed to maximum of 79 mph. In some locations bridges are improved and switches removed
Under construction
2009
$1.5 M*
Raleigh to Selma
H-80.1 to H-109.3
Increase curve superelecation and crossing warning times for 79 mph.
Under construction
2009
$2 M*
Hopson Rd. Grade Separation & Railroad Realignment
H-64.2 to H-65.3
Realign railroad, build bridge over Hopson Rd, close Church St. Crossing & extend Church St. to Hopson Rd.
Finalizing environmental document & public involvement
2012
$10 M
Haw River
H-23.5 to H-25.5
Build 10,000 feet of new track to create a passing siding. As part of the project, four curves will be straightened
Preliminary plans & environmental work complete. Final design underway. R/W acquisition to begin 2009.
2012
$12 M*
Thomasville to Lexington
(Bowers to Lake)
309.8 to 314.0
Construct second main track to improve railroad capacity and passenger train reliability.
Preliminary engineering
2012
$13 M*
Concord to Charlotte
(Haydock to Junker)
360.0 to 372.2
Construct second main track to improve railroad capacity and passenger train reliability.
Preliminary engineering
2012
$30 M*
Salisbury to Kannapolis
(Reid to N. Kannapolis)
337.3 to 347.3
Construct second main track to improve railroad capacity and passenger train reliability.
Preliminary engineering
2013
$22 M*
Completed Projects
Projects Underway
*
Denotes project cost estimate
Updated January 2009
NCRR Track Improvement Status